The Transport Ministry informs that 15 offers were submitted this Tuesday to design and construct sections 3 and 4 of the express road Craiova-Pitesti.
For section 3 there were eight offers from six associations and two constructors, says Agerpress. The section will have a length of 31,75 kilometers and will worth RON 904.819 million without VAT. Section 3 will be built between kilometer 57+550 and km 89+300 and it will link a few villages from Argest and Olt counties.
The contract will last for 96 months. The design period will last 12 months, the construction will be in the next 24 months and the last 60 months will be the period of validity.
For section 4 there were seven offers, all of them from the same companies that made offers for section 3. The section’s length will measure 31,81 kilometers and it will worth RON 909.6 million without VAT. Section 4 will intersect with Autostrada 1 Bucharest.
MT estimates that the entire express road will cost RON 3.7 billion without VAT.There were a total of 35 offers by now.
The contract for designing, construction and period of validity is the same as for the third section.
The project will be financed by the Infrastructura Mare 2014-2020 Operational Program.